Tafawa Balewa Primary School Renovation
Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.
Complete renovation of the primary school including new roofing, classroom furniture, installation of ceiling fans, and painting of all 12 classroom blocks. The project also includes construction of new toilet facilities and a borehole for clean water.
Site clearing and preparation
1 Oct 2025
Roofing replacement
15 Dec 2025
Furniture installation
1 Mar 2026
Borehole drilling
1 May 2026
Final inspection & handover
30 Jun 2026
No field updates yet
Updates will appear here as champions submit them.
No comments yet. Be the first to share your thoughts!
Allocated Budget
₦45,000,000
Amount Spent
₦28,000,000
Remaining
₦17,000,000
- Contractor
- Bashir Construction Ltd
- State
- Bauchi
- LGA
- Tafawa Balewa
- Start Date
- 15 Sept 2025
- Expected End
- 30 Jun 2026
- Nominated By
- Community
0
Votes
0
Comments
See something wrong?
If this project doesn't match reality on the ground, file a discrepancy report.