Katagum-Misau Road Rehabilitation
Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.
Rehabilitation of the 45km Katagum-Misau road including pothole filling, resurfacing, drainage construction, and installation of road signs and speed bumps in settlement areas.
Mobilization to site
15 Nov 2024
Drainage construction
30 Mar 2025
Road resurfacing
15 Jul 2025
Road furniture installation
1 Oct 2025
Final inspection & handover
28 Nov 2025
No field updates yet
Updates will appear here as champions submit them.
No comments yet. Be the first to share your thoughts!
Allocated Budget
₦250,000,000
Amount Spent
₦238,000,000
Remaining
₦12,000,000
- Contractor
- Nigerian Highway Constructors
- State
- Bauchi
- LGA
- Katagum
- Start Date
- 1 Nov 2024
- Expected End
- 30 Nov 2025
- Nominated By
- Community