Dass General Hospital Upgrade
Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.
Expansion and upgrade of Dass General Hospital including a new maternity ward, renovated outpatient department, procurement of essential drugs, and installation of a 100KVA generator for uninterrupted power.
Site survey and design approval
15 Apr 2025
Maternity ward construction
30 Aug 2025
Outpatient dept renovation
31 Jan 2026
Equipment procurement
30 Jun 2026
Generator installation & commissioning
30 Sept 2026
No field updates yet
Updates will appear here as champions submit them.
No comments yet. Be the first to share your thoughts!
Allocated Budget
₦180,000,000
Amount Spent
₦95,000,000
Remaining
₦85,000,000
- Contractor
- MediStruct Nigeria Ltd
- State
- Bauchi
- LGA
- Dass
- Start Date
- 1 Mar 2025
- Expected End
- 30 Sept 2026
- Nominated By
- Community
0
Votes
0
Comments