Pankshin-Kanke Road Construction

Pankshin, Plateau StatePlatRoads Engineering15 Feb 2025 15 Aug 2026

Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.

Project Description

Construction of a new 28km asphalt road connecting Pankshin and Kanke LGAs with bridges, culverts, and drainage systems.

Progress & Milestones
Overall Progress50%

Mobilization and site clearing

15 Apr 2025

Done

Bridge and culvert construction

31 Aug 2025

Done

Asphalt laying Phase 1 (14km)

31 Jan 2026

Asphalt laying Phase 2 (14km)

31 May 2026

Line marking & sign installation

15 Aug 2026

Field Updates

No field updates yet

Updates will appear here as champions submit them.

Discussion (0)

No comments yet. Be the first to share your thoughts!

Budget Breakdown

Allocated Budget

₦450,000,000

Amount Spent

₦225,000,000

Utilization50%

Remaining

₦225,000,000

Project Info
Contractor
PlatRoads Engineering
State
Plateau
LGA
Pankshin
Start Date
15 Feb 2025
Expected End
15 Aug 2026
Nominated By
Community
Community Engagement

0

Votes

0

Comments