Lafia Water Supply Network Expansion
Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.
Expansion of the water supply network to cover 15 additional communities in Lafia LGA. Includes laying of new pipelines, construction of 5 water treatment units, and installation of 20 community standpipes.
Survey and design
30 May 2025
Pipeline laying Phase 1
15 Sept 2025
Treatment unit construction
20 Dec 2025
Pipeline laying Phase 2
28 Feb 2026
Standpipe installation & testing
10 Apr 2026
No field updates yet
Updates will appear here as champions submit them.
No comments yet. Be the first to share your thoughts!
Allocated Budget
₦85,000,000
Amount Spent
₦52,000,000
Remaining
₦33,000,000
- Contractor
- Aqua Solutions Nigeria
- State
- Nasarawa
- LGA
- Lafia
- Start Date
- 10 Apr 2025
- Expected End
- 10 Apr 2026
- Nominated By
- Community
0
Votes
0
Comments