Nasarawa-Toto Farm Access Roads
Accountability champions can submit field updates anytime there is meaningful progress, evidence, or a blocker. Reminder nudges are advisory only and never block submissions.
Construction of 35km of farm access roads connecting major farming communities to trunk roads and market centers in Nasarawa and Toto LGAs.
Route survey and clearing
31 Mar 2025
Grading and compaction Phase 1
31 Jul 2025
Culvert installation
30 Sept 2025
Grading Phase 2
30 Nov 2025
Final grading and signage
31 Dec 2025
No field updates yet
Updates will appear here as champions submit them.
No comments yet. Be the first to share your thoughts!
Allocated Budget
₦165,000,000
Amount Spent
₦58,000,000
Remaining
₦107,000,000
- Contractor
- RuralRoads Nig. Ltd
- State
- Nasarawa
- LGA
- Nasarawa
- Start Date
- 10 Jan 2025
- Expected End
- 31 Dec 2025
- Nominated By
- Community